COLUMNS
|
- Wrap
the column with the specified number of wraps as calculated
and indicated on the specification. Wrap TOP first; BOTTOM
second or as per project specifications. Sequence to be advised
on daily work sheet for each column. Follow approved drawings.
- While
continuously wrapping, apply Hex-3R Wrap with uniform and
smooth pressure either with a stiff spatula or a surface roller,
securing and smoothing each layer.
|
|
BEAMS
(INCLUDING SHEAR STRENGTHENING)
|
- Wrap
the beam with the specified number of wraps as calculated
and indicated on the specification. Sequence to be advised
on daily work sheet for each beam. Follow approved drawings.
- Apply
shear strengthening layers on top of the flexural strengthening
layers or as per engineering drawings. This method helps to
secure the ends of the flexural strengthening.
- Install
FibrAnchors as per specifications if required.
|
|
WALLS
(INCLUDING URM WALLS)
|
- Apply
specified number of layers as calculated and indicated on
the specification. Application sequence to be advised on daily
work sheet. Follow approved drawings.
- Install
FibrAnchors as per specifications if required.
|
|
SLABS
|
- Apply
specified number of layers as calculated and indicated on
the specification. Application sequence to be advised on daily
work sheet. Follow approved drawings.
- Additional
set time may be necessary to properly adhere large sheets
of Hex-3R Wrap in overhead applications.
- Install
FibrAnchors as per specifications if required.
|
|
WALL/SLAB
CONNECTIONS
|
- Install
specified radius bedding of Hex-3R Epoxy at joint of wall
and slab, insuring that radius extends equally between the
wall and slab as per drawings. Allow the Hex-3R Epoxy to cure
overnight to a tacky, firm state.
- Apply
primer coat as per General Installation Instructions.
- Apply
Hex-3R Wrap with uniform and smooth pressure, either with
a stiff spatula or a surface roller, onto the wall/slab and
over the joint as per the drawings.
- Install
FibrAnchors as per specifications if required.
|